Measurement book format for civil works: the MB columns for Nos, L, B, D, how less lines are recorded, and how measurements move into an RA bill abstract.

Updated · RA BillCalc

The measurement book is the source document for every rupee in a running account bill. If a quantity cannot be traced to an MB page — dated, signed and measured at site — the bill is only as good as the person who typed it. This page covers the columns of a standard MB page, how less lines are recorded, and the path from the register to the abstract.

The columns on an MB page

Departments print their own register, but the working columns are consistent across CPWD-style works, state PWD and municipal engineering. A measurement line reads left to right as a sentence: how many, how long, how wide, how deep.

ColumnWhat goes in itWhy it matters
Serial / pageThe MB number and page number, continued across billsA bill cites these pages; a fresh page per item breaks the trail
DateThe date the work was measured, not the date it was written upMeasurement date versus bill period decides what is payable now
DescriptionItem, location and what was measured, in wordsLinks the line to a BOQ item and to a drawing
NosHow many identical piecesTen columns measured once is 10 in Nos, not ten repeated lines
L / B / DLength, breadth and depth or height, in metresUnits are metres in the register, even when the item is billed in sqm or cum
QuantityNos × L × B × D, to two decimals, with the unit of the itemThe number that is carried to the abstract
RemarksDrawing number, "less opening", contractor's representative presentExplains unusual lines when the bill is checked months later

A page, worked

Suppose the site has a 10 m long, 2.7 m high brick wall, 230 mm thick, with one door and one window opening. The register reads:

DescriptionNosLBDQuantity
Brickwork in CM 1:6, north wall, ground floor110.000.232.706.21 cum
Less: door opening 1.0 × 2.111.000.232.10−0.48 cum
Less: window opening 1.2 × 1.211.200.231.20−0.33 cum
Net brickwork for the item5.40 cum

Note where the rounding happens: each line is rounded to two decimals before the less lines are subtracted. 0.3312 becomes 0.33; the untouched raw value would give 5.3988 and print as 5.40, but the line-by-line method is what a departmental check reproduces, and it is what the calculator applies.

From the register to the RA bill

  1. Measure, then write. Record dimensions at site with the contractor's representative present; do not reconstruct a page from memory at the end of the month.
  2. Close the page with an abstract. Most registers have a summary at the foot of the page or at the end of the measurement: each item, its total quantity and the MB reference.
  3. Carry quantities to the bill abstract. Group the lines by BOQ item. For a second bill, the item quantity this month plus the cumulative quantity already billed gives the up-to-date figure.
  4. Cite the pages. Every bill row should be traceable to the MB pages measured in that period. If a quantity was measured earlier but billed late, say so — otherwise it looks like a double measurement.
  5. Attach the abstract, not the whole book. The bill goes for check with the measurement abstract and MB references; the register itself stays in the division.

Errors that cost a month

  • Mixing units. Register in metres, but billing a 230 mm wall as "0.23" is right while billing it as "230" turns cubic metres into something else entirely.
  • Netting the less lines by hand. Writing "6.21 − 0.81 = 5.40" in the description loses the audit trail; the openings need their own lines.
  • One page for every item. The register is chronological by measurement, not by BOQ item. Grouping by item at write-up time is what causes omitted measurements.
  • Overwriting instead of striking out. A corrected dimension is struck through, initialled and re-written. An erased figure is treated as an unauthorised change.
  • No date. A measurement without a date cannot be assigned to a bill period, and the quantity either gets billed twice or not at all.
The physical register — or the division's e-measurement system — remains the record of account. A spreadsheet or calculator is a way to do the arithmetic quickly; it does not replace the signed MB.

Once the quantities are agreed, the remaining work is the abstract: the RA bill format guide shows the three parts, and the Excel template gives you one row per MB line with the quantities calculated for you.

Questions people ask

What is a measurement book?

A measurement book — MB — is the site register in which the junior engineer records the actual dimensions of work done: Nos, length, breadth and depth for each item, with the date and location. The quantities in an RA bill come from these pages, so an unsigned or untidy MB is the usual reason a bill stalls.

What are the columns in a measurement book?

Typically: serial number, date, description of the item with its location, Nos, length, breadth, depth or height, quantity, and remarks or a reference to the drawing and page. The exact printed columns differ by department, but those fields are always present.

Who writes the measurement book?

The junior engineer or the section officer responsible for the site records the measurements, usually in the presence of the contractor or their representative. The assistant engineer checks and signs the abstract at the end of the measurement.

Is a digital measurement book accepted?

Some divisions accept e-measurement or a digital MB, others insist on the physical register and accept only the printed abstract from it. Ask the division before switching formats; the bill should always be able to cite the MB page it came from.

How do deduct lines appear in the MB?

As separate measurement lines marked "less" — for example a wall measurement followed by a less line for the door opening. In a bill, each less line should stay separate until the item quantity is totalled, so the checking engineer can see why the quantity is lower.

Do the arithmetic without a spreadsheet