A running account bill — RA bill — is the interim payment a contractor claims while work is still going on. Every department prints its own version, but almost all of them follow the same three-part skeleton: Part A for the work done, Part B for the deductions, and Part C for the net payable. Get those three parts right and the bill clears the measurement check; get a column wrong and it comes back.

The three parts at a glance

PartWhat it holdsWhere the numbers come from
A — Work done Each BOQ item with its rate, quantity up to the previous bill, quantity in this bill, total quantity and amount Measurement book pages, item rates from the agreement
B — Deductions Retention or security deposit, mobilisation advance recovery, TDS under section 194C, labour cess Percentages fixed in the agreement or by statute, applied to the gross
C — Net payable Gross minus total deductions, plus the amount in words and signature blocks Arithmetic from Parts A and B

Part A: columns of the work-done statement

Part A is a table, one row per BOQ item. The order of the columns matters less than having all of them, because the checking engineer reads across the row to confirm three things: the rate matches the agreement, the quantity matches the measurement book, and the amount matches quantity × rate.

ColumnWhat to writeCheck
Item no.The BOQ item number, unchangedDo not renumber mid-contract
DescriptionThe BOQ description, not a paraphraseUnits must match the BOQ (cum, sqm, kg, each)
RateThe agreement rate, to the paisaAny rate change needs a variation order
As per BOQThe tendered quantityUsed to flag overruns
Up to previous billCumulative quantity already paidCopy from the last bill, do not recompute
This billQuantity measured since the last billMust tie to the MB pages cited
TotalPrevious + this billMust not silently exceed the BOQ without approval
AmountThis-bill quantity × rate, rounded to the paisaRound only here, not in the quantity

A worked RA bill you can check by hand

Here is a small second bill — RA-2 — with the same numbers the free calculator produces when you load its example. Agreement amount ₹42,00,000; retention 5%, advance recovery 10%, TDS 2%, labour cess 1%.

ItemUnitRateThis billAmount
Earthwork excavation in ordinary soilcum180.0048.608,748.00
PCC 1:4:8 in foundationscum4,850.004.0519,642.50
Brickwork in cement mortar, openings deductedcum6,200.005.4033,480.00
12 mm cement plastersqm215.00120.0025,800.00
Gross amount of this bill87,670.50

The brickwork row is the one people get wrong. Three measurement lines feed it: 1 × 10 × 0.23 × 2.7 for the wall, less 1 × 1 × 0.23 × 2.1 for one opening, less 1 × 1.2 × 0.23 × 1.2 for another. Each line is rounded to two decimals before subtraction, which gives 6.21 − 0.48 − 0.33 = 5.40 cum.

Part B, on the same gross

DeductionRateAmount
Retention5%4,383.53
Mobilisation advance recovery10%8,767.05
TDS under section 194C2%1,753.41
Labour cess1%876.71
Total deductions18%15,780.70

Part C, net payable

₹87,670.50 − ₹15,780.70 = ₹71,889.80, written as Rupees seventy-one thousand eight hundred eighty-nine and paise eighty only. The words are part of the format, not a formality: a mismatch between figures and words is one of the most common reasons a bill is returned.

The deduction percentages above follow the calculator's defaults. Your agreement may use 10% retention, a different advance recovery schedule, or no cess. Read the agreement before copying any percentage. The deduction guide explains each base and typical rate.

Which format should you actually use?

The departmental printed form always wins. A bill typed in the calculator's CPWD-style layout is a working abstract and a cross-check, not a substitute for the form your division issues.

  • CPWD and CPWA-format divisions — the running account bill is Form 26; the final bill is Form 27. What Form 26 contains.
  • State PWD divisions — each state prints its own abstract, and column headings differ. Ask the division for the current form and mirror it.
  • Municipal and panchayat works — often a simpler abstract with the same three parts; the schedule of rates and the agreement still control the rates.

Five mistakes that send a bill back

  1. Deduct lines left out. Door and window openings, or any "less" measurement, must appear as separate negative lines. Netting them by hand in the description is how brickwork quantities inflate.
  2. Rounding in the wrong place. Round the quantity to two decimals, then multiply by the rate and round the amount. Rounding the dimensions themselves changes the quantity.
  3. Applying deductions to the net. Each percentage applies to the gross work-done value; applying them one after another under-deducts every time.
  4. Recomputing the previous quantity. Copy the cumulative figure from the last bill. Recomputation picks up any corrected measurement twice.
  5. Figures that do not match the words. Generate the amount in words from the final net, not from an earlier draft.

Making one without retyping the sums

The free RA bill calculator takes the measurement lines, applies the four deductions and prints this exact structure — Part A, Part B, Part C, words and signature blocks — on A4. If you would rather keep it in a spreadsheet, the Excel layout and formulas are here.

Printed RA bill abstract with Part A items, Part B deductions and Part C net payable, on A4
The printed abstract from the calculator: work done, deductions, net payable and amount in words on one A4 page.

Questions people ask

What is the full form of RA bill?

Running Account bill. It is the interim bill a contractor raises for work done between two dates while the work is still going on. The final bill settles the whole contract at the end.

Is an RA bill the same as a running bill?

Yes. Running bill, part bill and interim bill all mean the same thing in practice. Some departments number the form itself — CPWD uses Form 26 for a running account bill — but the three-part structure is the same.

What are Part A, Part B and Part C of an RA bill?

Part A lists the work done and its value. Part B lists the deductions — retention or security deposit, recovery of mobilisation advance, TDS under section 194C and labour cess. Part C is the net amount payable, also written in words.

Should retention be calculated on the gross bill or on the net?

On the gross value of work done in this bill, unless your agreement says otherwise. Each deduction is applied to the same gross and the four amounts are added; the total is then subtracted once to reach the net payable.

Who signs an RA bill?

Typically the contractor or their authorised person, the junior engineer who measured the work, and the assistant engineer or executive engineer who checks and passes it. The exact signature blocks differ by department, so use the printed form your division supplies.

Do the arithmetic without a spreadsheet

Enter the measurement lines, set the four deductions, and print the abstract. Free, no signup, nothing leaves your browser.

Open the RA bill calculator